Location: Gulf of Mexico
Project date: Mar 2023 to Apr 2023
Drilling duration: 39 days
Total footage drilled: 16,143ft

OVERVIEW

A leading offshore exploration and production company with Deepwater and shallow water assets in the Gulf of Mexico contracted TEMS International to support drilling operations.

TEMS Technical Environmental Specialists oversaw all drilling operations and recorded all subsequent information.

The overall aims of the project were to:

  • Achieve governmental oil on wet cuttings (OOWC) limitations in line with EPA reporting
  • Optimise solids control equipment to deliver maximum solids removal with minimum liquid retention
  • Reduce synthetic based mud surface consumption
  • Reduce shaker screen consumption
  • Minimise environmental impact
  • Reduce carbon footprint
1,984.80  > Fewer barrels of mud used
$375,127.00 > Saved on mud costs
$1,737,970.00 > Waste fluid savings
4.25% > Final well ROC %

All objectives achieved without the use of a cuttings dryer package.