A selection of historical data exploring projects recently completed by TEMS International.
TEMS International Historical Data 81

HISTORICAL DATA 81

A leading offshore exploration and production company with deepwater and shallow water assets in the Gulf of Mexico contracted TEMS International to support drilling operations from November 2022 to January 2023.
TEMS International Historical Data 84

HISTORICAL DATA 84

A leading offshore exploration and production company with deepwater and shallow water assets in the Gulf of Mexico contracted TEMS International to support drilling operations from March to April 2023.
TEMS International Historical Data 77

HISTORICAL DATA 77

A leading offshore exploration and production company with deepwater and shallow water assets in the Gulf of Mexico contracted TEMS International to support drilling operations from October – November 2022.
TEMS International Historical Data 78

HISTORICAL DATA 78

A leading offshore exploration and production company with deepwater and shallow water assets in the Gulf of Mexico contracted TEMS International to support drilling operations from October – December 2022.
TEMS International Historical Data 79

HISTORICAL DATA 79

A leading offshore exploration and production company with deepwater and shallow water assets in the Gulf of Mexico contracted TEMS International to support drilling operations from November 2022 to January 2023.
TEMS International Historical Data 75

HISTORICAL DATA 75

A leading offshore exploration and production company with deepwater and shallow water assets in the Gulf of Mexico contracted TEMS International to support drilling operations in October 2022.  During the 19-day project, TEMS International engineers oversaw more than 4,973ft of drilling from a drill ship.
TEMS International Historical Data 73

HISTORICAL DATA 73

A leading offshore exploration and production company with deepwater and shallow water assets in Malaysia contracted TEMS International to support drilling operations in January 2022.  During the 188-day project, TEMS International engineers oversaw more than 10,625ft of drilling from a jack-up.
TEMS International Historical Data 70

HISTORICAL DATA 70

A leading offshore exploration and production company with deepwater and shallow water assets in the Gulf of Mexico contracted TEMS International to support drilling operations from February – May 2022. During the 92-day project, TEMS International engineers oversaw more than 24,000ft of drilling from a drill ship.
TEMS International Historical Data 68

HISTORICAL DATA 68

A leading offshore exploration and production company with deepwater and shallow water assets in the Gulf of Mexico contracted TEMS International to support drilling operations from April 2021 to April 2022. During the 370-day project, TEMS International engineers oversaw more than 32,000ft of drilling from a drill ship.
TEMS International Historical Data 67

HISTORICAL DATA 67

A leading offshore exploration and production company with deepwater and shallow water assets in the Gulf of Mexico contracted TEMS International to support drilling operations from February – May 2022. During the 95-day project, TEMS International engineers oversaw more than 13,000ft of drilling from a jack-up rig.
TEMS International Historical Data 63

HISTORICAL DATA 63

A leading offshore exploration and production company with deepwater and shallow water assets in the Gulf of Mexico contracted TEMS International to support drilling operations from October - December 2021. During the 89-day project, TEMS International engineers oversaw more than 21,000ft of drilling from a drill ship.
TEMS International Historical Data 61

HISTORICAL DATA 61

A leading offshore exploration and production company with deepwater and shallow water assets in Malaysia contracted TEMS International to support drilling operations from April to August 2021. During the 221-day project, TEMS International engineers oversaw more than 15,000ft of drilling from a jack-up rig.
TEMS International Historical Data 60

HISTORICAL DATA 60

A leading offshore exploration and production company with deepwater and shallow water assets in the Gulf of Mexico contracted TEMS International to support drilling operations from April to August 2021. During the 217-day project, TEMS International engineers oversaw more than 27,000ft of drilling from a drill ship.
TEMS International Historical Data 59

HISTORICAL DATA 59

A leading offshore exploration and production company with deepwater and shallow water assets in Gulf of Mexico contracted TEMS International to support drilling operations from October - November 2021. During the 27-day project, TEMS International engineers oversaw more than 2,500ft of drilling from a drill ship.
TEMS International Historical Data 58

HISTORICAL DATA 58

A leading offshore exploration and production company with deepwater and shallow water assets in Malaysia contracted TEMS International to support drilling operations from April to November 2021. During the 193-day project, TEMS International engineers oversaw more than 13,000ft of drilling from a jack-up rig.
TEMS International Historical Data 57

HISTORICAL DATA 57

TEMS International was contracted by a Malaysian oil and gas company focused on gas production in the waters off the Asian country to support drilling operations during 2021. During the 162-day project, TEMS International engineers oversaw 11,200ft of drilling onboard the drill ship.
TEMS International Historical Data 56

HISTORICAL DATA 56

TEMS International was appointed by an exploration and production company focused on developing oil and gas assets in the deepwater Gulf of Mexico to support drilling operations onboard a drill ship in the region. Run over 40 days in August and September 2021, TEMS International engineers oversaw nearly 9,000ft of drilling.
TEMS International Historical Data 55

HISTORICAL DATA 55

In 2021, TEMS International was contracted by an existing client, a leading international E&P company, to support a drilling and completions programme in the Gulf of Mexico. The deepwater project was undertaken in July 2021, with TEMS International engineers overseeing more than 2,200ft of drilling.
TEMS International Historical Data 54

HISTORICAL DATA 54

A Malaysian oil and gas company focused on gas production in the waters off the Asian country engaged the services of TEMS International to support drilling operations during 2021. Over 5,500ft of drilling was overseen by TEMS International engineers while onboard the drill ship during the 137-day project.
TEMS International Historical Data 53

HISTORICAL DATA 53

A leading offshore exploration and production company with deepwater and shallow water assets in the Gulf of Mexico contracted TEMS International to support drilling operations from April to August 2021. During the 126-day project, TEMS International engineers oversaw more than 26,000ft of drilling from a drill ship.
TEMS International Historical Data 52

HISTORICAL DATA 52

A leading offshore exploration and production company with deepwater and shallow water assets in the Gulf of Mexico contracted TEMS International to support drilling operations in June – July 2021. During the 17-day project, TEMS International engineers oversaw more than 5,700 ft of drilling from a drill ship.
TEMS International Historical Data 50

HISTORICAL DATA 50

A leading offshore exploration and production company with deepwater and shallow water assets in Trinidad contracted TEMS International to support drilling operations from December 2020 – June 2021. During the 180-day project, TEMS International engineers oversaw more than 4,500ft of drilling from a jack up.
TEMS International Historical Data 49

HISTORICAL DATA 49

A leading offshore exploration and production company with deepwater and shallow water assets in Trinidad contracted TEMS International to support drilling operations from December 2020 to April 2021. During the 134-day project, TEMS International engineers oversaw more than 10,000 ft of drilling from a jack up.
TEMS International Historical Data 48

HISTORICAL DATA 48

A leading offshore exploration and production company with deepwater and shallow water assets in Malaysia contracted TEMS International to support drilling operations in June 2021. During the 18-day project, TEMS International engineers oversaw more than 13,000ft of drilling from a jack up.
TEMS International Historical Data 47

HISTORICAL DATA 47

A leading offshore exploration and production company with deepwater and shallow water assets in the Gulf of Mexico contracted TEMS International to support drilling operations in May 2021. During the 18-day project, TEMS International engineers oversaw more than 4,500ft of drilling from a drill ship.
TEMS International Historical Data 46

HISTORICAL DATA 46

A leading offshore exploration and production company with deep water and shallow water assets in Malaysia contracted TEMS International to support drilling operations in May 2021. During the 32-day project, TEMS International engineers oversaw over 7,500 ft of drilling from a jack-up.
TEMS International Historical Data 43

HISTORICAL DATA 43

A leading offshore exploration and production company with deepwater and shallow water assets in Trinidad contracted TEMS International to support drilling operations from December 2020 to March 2021. During the 102-day project, TEMS International engineers oversaw more than 5,600 ft of drilling from a jack up.
TEMS International Historical Data 41

HISTORICAL DATA 41

A leading offshore exploration and production company with deepwater and shallow water assets in the Gulf of Mexico contracted TEMS International to support drilling operations from December 2020 to January 2021. During the 47-day project, TEMS International engineers oversaw more than 22,000ft of drilling from a drill ship.
TEMS International Historical Data 40

HISTORICAL DATA 40

A leading offshore exploration and production company with deepwater and shallow water assets in Trinidad contracted TEMS International to support drilling operations from November 2020 to March 2021. During the 99-day project, TEMS International engineers oversaw more than11,900 ft of drilling from a jack up.
TEMS International Historical Data 39

HISTORICAL DATA 39

A leading offshore exploration and production company with deepwater and shallow water assets in Trinidad contracted TEMS International to support drilling operations from December 2020 to April 2021. During the 78-day project, TEMS International engineers oversaw more than 26,000ft of drilling from a drill ship.
TEMS International Historical Data 38

HISTORICAL DATA 38

A leading offshore exploration and production company with deepwater and shallow water assets in the Gulf of Mexico contracted TEMS International to support drilling operations from December 2020 to January 2021.  During the 52-day project, TEMS International engineers oversaw more than 6,150ft of drilling from a drill ship.
TEMS International Historical Data 37

HISTORICAL DATA 37

A leading offshore exploration and production company with deepwater and shallow water assets in the Gulf of Mexico contracted TEMS International to support drilling operations from November 2020 to January 2021. During the 56-day project, TEMS International engineers oversaw more than 13,548 ft of drilling from a drill ship.
TEMS International Historical Data 36

HISTORICAL DATA 36

A leading offshore exploration and production company with deepwater and shallow water assets in the Gulf of Mexico contracted TEMS International to support drilling operations from August to November 2020. During the 93-day project, TEMS International engineers oversaw more than 17,000ft of drilling from a drill ship.
TEMS International Historical Data 34

HISTORICAL DATA 34

A leading offshore exploration and production company with deepwater and shallow water assets in Trinidad contracted TEMS International to support drilling operations from August to October 2020. During the 81-day project, TEMS International engineers oversaw more than 14,000ft of drilling from a drill ship.
TEMS International Historical Data 33

HISTORICAL DATA 33

A leading offshore exploration and production company with deepwater and shallow water assets in the Gulf of Mexico contracted TEMS International to support drilling operations in July and August 2020. During the 44-day project, TEMS International engineers oversaw more than 10,600ft of drilling from a drill ship.
TEMS International Historical Data 32

HISTORICAL DATA 32

A leading offshore exploration and production company with deepwater and shallow water assets in the Gulf of Mexico contracted TEMS International to support drilling operations in April and May 2020. During the 59-day project, TEMS International engineers oversaw more than 15,000ft of drilling from a drill ship.
TEMS International Historical Data 30

HISTORICAL DATA 30

An exploration and production company focused on developing oil and gas assets in the deepwater Gulf of Mexico appointed TEMS international to a support drilling project onboard a drill ship in the region. The 28-day project commenced in late May 2020, during which time TEMS International engineers oversaw over 4,700ft of drilling.
TEMS International Historical Data 29

HISTORICAL DATA 29

In June 2019, TEMS International commenced work with a US-headquartered exploration and production company to support drilling operations onboard a drill ship in the Gulf of Mexico. The project ran for 47 days, during which time TEMS International engineers oversaw 7,500ft of drilling.
TEMS International Historical Data 28

HISTORICAL DATA 28

An independent global exploration and production company contracted TEMS International to support its drilling operations onboard a SPAR platform in the Gulf of Mexico. The project got underway in December 2019, continuing for 45 days. during which time over 3,000ft of drilling was overseen by TEMS International engineers.
TEMS International Historical Data 27

HISTORICAL DATA 27

An exploration and production company focused on developing oil and gas assets in the deepwater Gulf of Mexico appointed TEMS international to a support drilling project onboard a drill ship in the region. Commencing in January 2020, TEMS International engineers oversaw over 18,000ft of drilling during the 61-day project.
TEMS International Historical Data 24

HISTORICAL DATA 24

TEMS International was contracted by an existing client – a US-based, independent exploration and production company – to support drilling operations onboard a drill ship in the Gulf of Mexico. The deepwater project ran over 23 days in September and October 2019, when over 3,800ft of drilling was overseen by TEMS International engineers.
TEMS International Historical Data 23

HISTORICAL DATA 23

In 2019, a leading international E&P company contracted TEMS International to support its drilling campaign on a well in offshore Trinidad. The deepwater exploration project commenced in August and concluded 48 days later. During this time TEMS International engineers oversaw nearly 3,500ft of drilling.
TEMS International Historical Data 22

HISTORICAL DATA 22

In 2019, TEMS International supported the drilling of an exploratory well in offshore Trinidad by a leading international E&P company. The deepwater project was carried out over 37 days in August and September, during which time TEMS International engineers oversaw over 5,800ft of drilling.
TEMS International Historical Data

HISTORICAL DATA 21

An independent exploration and production company headquartered in the United States contracted TEMS International to support drilling operations onboard a rig in the Gulf of Mexico. The project commenced in March 2019 and concluded in August after 164 days of drilling activity. During this time, TEMS International engineers oversaw over 16,000ft of drilling.
TEMS International Historical Data

HISTORICAL DATA 18

An existing client, a US-based independent exploration and production company, contracted TEMS International to support drilling operations onboard a rig in the Gulf of Mexico. The 47-day drilling project commenced in June 2019 and involved approximately 7,500ft of drilling which was overseen by TEMS International engineers.
TEMS International Historical Data

HISTORICAL DATA 15

An independent global exploration and production company contracted TEMS International to support exploratory drilling of a well in offshore Trinidad in 2019. The deepwater project concluded in July 2019 after more than 100 days, during which time nearly 4,900ft of drilling was overseen by TEMS International engineers.
TEMS International Historical Data

HISTORICAL DATA 13

TEMS International was contracted by an existing client – an independent global exploration and production company – to support exploratory drilling operations in offshore Trinidad. The deepwater project commenced in February 2019 and continued for 73 days. Over 5,500ft of drilling was overseen by TEMS International engineers during this time.
TEMS International Historical Data

HISTORICAL DATA 12

TEMS International was approached by an independent global exploration and production company to support its drilling operations in the Gulf of Mexico. The project commenced in May 2019 and continued for 24 days, during which time TEMS International engineers oversaw over 4,500ft of drilling.
TEMS International Historical Data

HISTORICAL DATA 9

TEMS International was contracted by an existing client – an independent global exploration and production company – to support exploratory drilling operations in offshore Trinidad. The deepwater project commenced in March 2019 and lasted for 52 days. During the project, over 5,500ft of drilling was overseen by TEMS International engineers.
TEMS International Historical Data

HISTORICAL DATA 8

TEMS International was approached by an independent exploration and production company to support its drilling operations in the Gulf of Mexico. The drilling project commenced in May 2019 and lasted for 20 days. During the project, around 3,800ft of drilling was overseen by TEMS International engineers.
TEMS International Historical Data

HISTORICAL DATA 6

TEMS International was approached by an existing client – an independent global exploration and production company – to support drilling operations in offshore Mexico. The deepwater project commenced in November 2018 and lasted for 78 days. During the project, more than 9,500ft of drilling was overseen by our engineers.
TEMS International Historical Data

HISTORICAL DATA 5

TEMS International supported an independent global exploration and production company during the drilling of a well in the Gulf of Mexico. The deepwater project commenced in November 2018 and continued for 44 days. During the project, TEMS International engineers oversaw more than 15,500ft of drilling.
TEMS International Historical Data

HISTORICAL DATA 4

TEMS International supported an independent global exploration and production company during the drilling of an exploratory deepwater well in offshore Trinidad and Tobago. The project began in October 2018 and lasted 20 days with no hydrocarbons being encountered. During the project, engineers oversaw about 3,750ft of drilling.
TEMS International Historical Data

HISTORICAL DATA 3

TEMS International supported an independent global exploration and production company during the drilling of a deepwater well in offshore Trinidad and Tobago. The project, which commenced in July 2018, lasted for 56 days, during which time TEMS International engineers oversaw more than 7,000ft of drilling.
TEMS International Historical Data

HISTORICAL DATA 2

TEMS International was contracted by an independent exploration and production company to support the drilling of a well in the Gulf of Mexico. The project, which commenced in March 2019, lasted for 252 days, during which time TEMS International engineers oversaw more than 17,500ft of drilling.
TEMS International Historical Data

HISTORICAL DATA 1

TEMS International was contracted by an independent global exploration and production company to support the drilling of a deepwater well in the Gulf of Mexico. The project, which commenced in April 2018, lasted for 183 days, during which time TEMS International engineers oversaw more than 48,000ft of drilling.